The Delivery-Risk Ranking: 20 South Florida Projects by Construction Status — Q4 2026

By Haute Residence Editorial ·

Every sales gallery quotes a delivery year. Concrete does not negotiate. This ranking sorts 20 tracked South Florida projects into four risk tiers by what has actually been built and financed as of September 2026 — the framework buyers should use before wiring a deposit against any promised date. Method: Tier 1 = topped out; Tier 2 = vertical construction underway; Tier 3 = ground broken / financing closed; Tier 4 = selling with no verified construction milestone. Within tiers, sooner published delivery ranks higher.

Tier 1 — Topped out: the date is earned

ProjectMarketMilestonePublished delivery
Rosewood Residences Hillsboro BeachHillsboro BeachTopped out Feb 2026Early 2027
The PerigonMiami BeachTopped out Mar 20262027
Waldorf Astoria Pompano BeachPompano BeachTopped out May 20262027
Cipriani Residences MiamiBrickellTopped off Jul 2026 · 80%+ soldSummer 2027
South Flagler HouseWest Palm BeachTopped out Nov 2025Late 2026–2027
Ocean House SurfsideSurfsideTopped out Aug 20262027

Tier 1: remaining risk is finish-out and inspections, not structure.

Tier 2 — Vertical: real, with runway risk

ProjectMarketMilestonePublished delivery
Mr. C ResidencesWest Palm Beach16 of 27 floors (Aug 2026) · 85%+ sold2027
Villa MiamiEdgewater21 of 56 floors (Jan 2026)Late 2027
OlaraWest Palm BeachVertical · $175M presoldQ4 2026–2027
Rivage Bal HarbourBal HarbourUnder construction2027
Waldorf Astoria MiamiDowntown MiamiUnder construction (supertall)2027
St. Regis BrickellBrickellUnder construction2027
Bentley ResidencesSunny Isles BeachPassed level 7 of 62 (Jun 2026) · $630M loan2028

Tier 2: structure rising; compare floors built against floors promised and the calendar.

Tier 3 — Ground broken / financed

ProjectMarketMilestonePublished delivery
Ritz-Carlton Residences WPBWest Palm BeachBroke ground Mar 2026 · $200M loan2028
The LincolnCoconut GroveStarted Jun 2026 · $58M loan · 40%+ soldQ3 2028
ShorecrestWest Palm BeachBroke ground Apr 20262027
Four Seasons Coconut GroveCoconut GroveSales launched2027

Tier 3: financing verified; the calendar test comes with vertical progress.

Tier 4 — Selling, no verified milestone

ProjectMarketStatusPublished delivery
619 Brickell (Nobu)BrickellSelling2031
Delano ResidencesDowntown MiamiSelling2031
Faena ResidencesMiami RiverSelling ($250M penthouse collection)2029

Tier 4 is not an accusation — long-dated projects are supposed to be here. Risk arises when a near-dated promise sits in this tier.

How should buyers use this ranking?

Match the tier to the promise. A 2027 date in Tier 1 is bankable; a 2027 date in Tier 3 deserves hard questions; a 2031 date in Tier 4 is simply honest. Deposit exposure should scale the same way — Florida escrow rules protect the first 10% differently from construction-usable funds, covered in our deposits guide.

One more signal: between August and September 2026 we recorded no formal date slips among tracked 2027 claimants — but five of fourteen 2027 claims are concrete-verified. The other nine have four quarters to earn their dates. We re-run this ranking quarterly.

Frequently Asked Questions

Which South Florida projects are most likely to deliver on time?

The topped-out tier: Rosewood Hillsboro, The Perigon, Waldorf Pompano, Cipriani, South Flagler House and Ocean House Surfside — structure complete, dates targeted for 2026–2027 (as of September 2026).

Have any major projects announced delays in 2026?

Between August and September 2026, no formal delivery-date changes were recorded among the fourteen tracked projects claiming 2027. The risk is concentrated in claims not yet backed by vertical construction.

What is the difference between topping out and topping off?

Interchangeable in practice: the structural frame has reached full height. It is the strongest single schedule signal in pre-construction — remaining work is enclosure, interiors and inspections.

How protected is my deposit if a project is delayed?

Florida law requires the first 10% held in escrow; amounts above 10% may be used for construction with proper disclosure. Delay alone rarely triggers refund rights — your contract’s outside date does. Have a Florida condo attorney read it before signing.

Should I avoid Tier 4 projects entirely?

No — long-dated projects (2029–2031) belong there naturally, often with the friendliest pricing and deposit terms. The red flag is a near-term delivery promise without a construction milestone behind it.

How often is this ranking updated?

Quarterly, with monthly milestone tracking in the Delivery Calendar series. Status lines here are as of September 21, 2026.